Videos and notes added by Daddy.
28 October test film
29 October – preparing the sub-base
30 October – the camera tie slipped down!
31 October – camera tie gets cleared! MBC arrive on site
1 November – MBC sub-base and pipework laid within sub-base
2 November – frosty morning! Preparing the foundations for the stonework
3 November – pouring the foundations for the stonework (and camera view gets partially blocked!)
4 November – preparing the insulated blocks
5 November – laying the insulated blocks
6 November – adding the DPC and DPM, more insulation blocks and the metal grids (once the condensation clears the lens!)
7 November – a wet and windy day, so no work on site (but the building inspector visits at 11.30am…)
8 November – another blustery day, foundations for electricity cabinet are put in
9 November – another blustery day, just a couple of site visits/inspections
10 November – no video but the underfloor heating pipes are laid that day – clipped onto the metal grids…
12 November – main raft foundation concrete pour
13 November – power floating (concrete finishing) and start of scaffolding
15 November – finishing the scaffolding